Wird geladen...
Wird geladen...
In Germany, battery energy storage systems are mostly approved as unregulated special structures. This article puts planning law, building regulations and the outer-area privilege adopted at the end of 2025 into context — and shows at which point in the procedure the fire protection verification is decisive.
Every storage project starts with urban planning law: does the site lie within the scope of a zoning plan, in the unzoned built-up inner area under section 34 of the German Federal Building Code (BauGB), or in the outer area under section 35 BauGB? Large-scale greenfield storage projects in particular long failed on the absence of a privileged status in the outer area and required a dedicated land-use planning procedure by the municipality.
At the end of 2025 the legislator addressed this: after an initial resolution in November 2025, the provision was given a differentiated form in December 2025. Battery storage systems are now privileged in the outer area if they have a spatial-functional connection with an existing renewable energy installation (section 35 (1) no. 11 BauGB). For storage without this connection, section 35 (1) no. 12 BauGB creates an additional privilege with area limits: the area occupied by all battery storage systems including ancillary facilities may not exceed 0.5 per cent of the municipal territory and, at the same time, 50,000 m². The privilege accelerates admissibility under planning law — but it replaces neither the building permit nor the fire protection verification.
No BImSchG Procedure
Stationary battery storage systems are currently not subject to permitting under the German Federal Immission Control Act, as they are not listed in the annex to the 4th BImSchV. The decisive approval procedure is the building permit procedure under the state building code — supplemented by grid connection with the network operator and registration in the core energy market data register.
Under building regulations there is a gap: apart from the model ordinance on the construction of operating rooms for electrical installations (M-EltBauV), whose scope was extended in spring 2022 to include energy storage systems in buildings, Germany has no dedicated building-code provisions for battery storage. Free-standing storage plants and storage parks do not fall under the M-EltBauV. Large-scale storage is therefore generally treated as a so-called unregulated special structure — the classification is made by the competent building permit authority case by case after expert consultation, and must not be assumed across the board.
Possible points of reference are in particular section 2 (4) no. 19 of the Model Building Code (installations with an increased fire or explosion hazard, for instance because of possible electrolyte off-gassing during thermal runaway) and no. 20 (electrical hazards). An exemption from the permit procedure, as applies to some building services installations, is not recognised by the expert community for large-scale lithium-ion storage. The practical consequence of the special-structure classification: the authority can impose particular requirements and grant relaxations in the permit procedure — fire protection thus becomes the central negotiating matter of the process.
For the fire protection assessment, a fire protection verification under section 11 of the model building document ordinance is regularly required in the building application procedure, for special structures usually in the form of a site-specific fire protection concept. Depending on state law, it is checked by the lower building supervisory authority or by approved checking engineers or inspection experts for fire protection; the fire brigade's fire protection office is involved.
The fire brigades' guidance documents — in particular the recommendations of the AGBF committee for preventive fire and hazard protection and the BVES safety guideline coordinated with the fire brigades (3rd edition 2025) — decisively shape the requirements in the procedure. Since a fire in a lithium-ion storage unit generally cannot be extinguished by the fire brigade but only prevented from spreading, the requirements target accessibility, water supply and safe operating conditions.
Coordinate Early Instead of Reworking Later
Experience from permit procedures shows: those who bring the fire protection office, the building permit authority and the property insurer to one table before submitting the building application, and agree distances, barriers, firefighting water and access routes by consensus, shorten the procedure considerably. Retrospective conditions on distances or structural separations can only be implemented on a fully designed plant at great expense.
Anton Brem
Managing Director
Refractory construction, high-temperature insulation and fire protection in industrial plants
Everything you need to know about Permitting and Building Law for Battery Storage in Germany: Where Fire Protection Enters the Procedure
Your question not listed?
Request a personal consultationWhether complete relining, repair or emergency — free initial consultation and a fast response.