Cupola furnace demolition in record time – safe preparation for the relining

A foundry near Tuttlingen was planning to reline its cupola furnace. This required the complete and professional demolition of the existing old lining. SBS Refractory Service was commissioned with the demolition work – a demanding task given the confined conditions at the furnace.
The cupola furnace offered only limited access for the demolition work
The old lining had to be removed without residue and without damaging the load-bearing furnace structure
Suitable equipment and experienced personnel were required for the confined conditions
The work had to be completed safely and on schedule to keep to the timetable for the relining
Our team prepared the assignment carefully and was on site with the right equipment. The demolition work was carried out systematically and in strict compliance with all safety requirements.
Despite the confined conditions at the cupola furnace, the team worked efficiently and in a coordinated manner. The old lining was removed completely and without residue, leaving the furnace structure undamaged.
The demolition was completed on schedule and the furnace was handed over prepared for the subsequent relining.

Systematic demolition of the old lining under confined conditions

Precise working methods for residue-free results

Cleanly prepared furnace – ready for the relining
The key figures of the “Demolition work on a cupola furnace near Tuttlingen” project
Whether complete relining, repair or emergency — free initial consultation and a fast response.